Leicester General Hospital Case Study

Kitchen and Chiller upgrade:

Upgrade of existing power and control system to the Kitchen, food storage and Food Prep areas

Removal of the existing Woodley system, Installation of new cable tray system for the installation of power, and control wiring to 22 no new room coolers.

Installation of power supplies to condense pumps supplied from BMS Control panel, power and control wiring to the Plant room area.

Installation of power and controls to three chiller units located adjacent to the plant room. Power to new BMS control panel, alteration to the existing control to existing Air handling units

Alteration to existing power and lighting.

Installation of tray work for the installation of the Rehau pipe work system to supply the new room cooler.